Error in period calculation whenMarch 28th 2016 is included

  • roosdaal
    Asked on January 11, 2016 at 6:15 AM

    A very strange issue is happening on a form i created at www.roosdaal.be/openbaardomein (dutch language).

    This form had fields for a start- and end-date and the next field calculates the nummer of days between them. This works just fine as long as the end date is before March 28th.

    When the end date is or exceeds March 28th, this day is calculated as 0.96 instead of 1 day?

    Enclosed screenshot shows result when March 28th is ending date (i have another screenshot showing March 27th, but i can onlu enclose one attachment)

     

    Jotform Thread 741285 Screenshot
  • Mike
    Replied on January 11, 2016 at 11:08 AM

    Thank you for contacting us.

    It appears that the issue has been already fixed on your form #52282860656360.

    Error in period calculation whenMarch 28th 2016 is included Image 1 Screenshot 20

    If you need any further assistance on this, please let us know.

  • victor
    Replied on January 12, 2016 at 8:20 AM

    Sorry for the inconvenience. I have just tested your form and was able to get the proper calculation of days. Could you please try clearing your cache and cookies of your browser.

    Error in period calculation whenMarch 28th 2016 is included Image 1 Screenshot 20

    If you are still having issues, please do let us know. We will be glad to take another look.