please tick where appropriate
1 Indoor unit correctly located coordinated with client
2 Outdoor unit correctly located and coordinated with client
3 Wall/Roof Penetration sealed from vermin and weather
4 Waffle pad under condensing unit feet or on plastic feet and bolted down.
5 Pipe work pressure tested if welding present only
6 Pipe work insulated; secured & flare nuts covered
7 Evacuation to less than 500 microns
8 Open both L/Line & Suction valves
9 Pour 2- 4 litres of water into the evaporator drain tray and check.
10 Condenser drain connected and running away from the house.
11 Configure wall controller to manufacturer's manual
12 Open remote control: insert batteries & set the clock
13 Add refrigerant according to pipe run refer manuf specs
14 Zone controller to be labelled correctly and tested for operation.
15 Explain to customer the requirement for annual servicing
16 Carry out site clean walls, replace furniture, pick up all off cuts
1
The details of the installation are correct and I agree to the terms and conditions
Indoor serial number
Outdoor serial number
Outdoor unit installation
Vacustat reading
Indoor unit installation
Controller installation
Signature:
Submit