GAS INSPECTION CHECKLIST
Is the meter bar or meter flange installed?
Is the gas line tied into the meter bar or flange?
Are all meter bas labeled for apartments they serve?
Are all appliance valves installed with plugs?
Do the number of appliance valves on the plan match with the number of gas valves on the riser?
Is all gas piping correctly supported?
Do all risers have riser clamps?
Is all pipe passing through walls sleeved?
Is the gas piping labeled every 5 feet?×
Are all gas risers supported at every floor?
Are all risers passing through concrete floors sleeved?
Is there any paint or coating on the gas pipe? If so has it been completely removed?
Are you testing the gas from the meter bar or meter flange to the appliance valves?
Is all equipment connected to the gas pipe?
Is all equipment properly vented?
Has the gas pipe passed a test at 3 PSI for 30 minutes?