Pre-Pour Inspection Checklist
Use the form below to make sure you are ready for concrete pouring!
Work location
Street Address
Street Address Line 2
City
State / Province
Postal / Zip Code
Nature and location of work to be inspected
Reinforcement and Installation
Yes
No
Notes
Is the Blinding/Formation level checked before installation?
1
2
Is all reinforcing installed clean and free of debris?
3
4
Have all the shear links been installed?
5
6
Is fixer forman available at the location at the time of inspection?
7
8
Has reinforcing steel been sampled and approved?
9
10
Is all reinforcing steel stored properly?
11
12
Formwork
Yes
No
Notes
Are forms in the proper location?
13
14
Are form dimensions correct?
15
16
Are Lines & Levels set out at the correct location per the current set of drawings?
17
18
Are Built Items installed at the correct location per the current set of drawings?
19
20
Are joint details including water bars installed per specification?
21
22
Has cover to reinforcement checked before Formwork?
23
24
Is the proper form release agent as defined in the specifications and approved submittals, on site in the work area and readily available in quantity necessary to cover the forms for the area of slab being placed?
25
26
Has the temporary work design been approved and Permit signed off?
27
28
Have f
orms works been installed to the drawings to insure that the slab, Vertical elements will be proper finish?
29
30
Are there any other slab penetrations that need to be verified by other trades?
31
32
If the product is a wall or column, has the correct type of form with the appropriate finish been used?
33
34
Is the area Clean from dust, debris, and Broken Tieing wires?
35
36
Is the Area safe for pouring?
37
38
Concrete
Yes
No
Notes
Have concrete trucks and plant been approved by Materials Lab within the last 12 months?
39
40
Have the contract’s hot and cold weather concrete batching and placement plans been accepted?
41
42
Are all concrete materials approved (cement, water, additives, fine and coarse aggregates, etc.)?
43
44
Are adequate curing and concrete protection materials on hand and placed ASAP (wet mats such as burlene, insulated blankets, external heaters with tarps, ice, etc)?
45
46
Have slump and air test been performed on each truck and have test cylinders been made?
47
48
Have all forms been wet down just prior to concrete placement?
49
50
Is the concrete truck mixing within specs (revolutions, air, slump, total water in mix, etc)?
51
52
Is the concrete vibrated properly?
53
54
Observations
Inspector name
First Name
Last Name
Phone number
Please enter a valid phone number.
Email
example@example.com
Signature
Submit
Should be Empty: