Pre-Pour Wall Inspection Checklist Form
Complete this checklist to document the pre-pour wall inspection before concrete is placed. All items are required for compliance and project records.
Inspector Name
*
First Name
Last Name
Inspection Date
*
 -
Month
 -
Day
Year
2 digit month, 2 digit day, 4 digit year
Date
Project/Site Name
*
Wall Location/Area
*
Formwork Condition (Clean, Correctly Installed, and Secure)
*
Satisfactory
Needs Attention
Reinforcement Placement (Correct Size, Spacing, and Supported)
*
Satisfactory
Needs Attention
Embedded Items (Conduits, Sleeves, Anchors) Installed and Secured
*
Satisfactory
Needs Attention
Wall Cavity Clean and Free of Debris/Water
*
Satisfactory
Needs Attention
Weather Conditions at Time of Inspection
*
Please Select
Clear
Cloudy
Rain
Snow
Other
Inspector Comments/Notes
Submit Inspection
Should be Empty: