Dispatch Log Book
Please enter the details for the feeder outage event.
Supervisor / Operator
*
First Name
Last Name
Feeders
*
Please Select
Bushrod Mt. Coffee 66kV TL-1
Bushrod Mt. Coffee 66kV TL-2
Bushrod Stockton Creek 66kV TL-1
Bushrod Stockton Creek 66kV TL-2
Bushrod Virginia 66kV TL-1
Bushrod Virginia 66kV TL-2
Bushrod Transformer #1 - 22kV Side
Bushrod Transformer #2 - 22kV Side
Bushrod Station Service
Bushrod Yard Service
Bushrod - Point 4
Bushrod - Port
Bushrod - Mount Coffee Express
Gardnersville Paynesville 66kV TL-1
Gardnersville Paynesville 66kV TL-2
Gardnersville Stockton Creek 66kV TL-1
Gardnersville Stockton Creek 66kV TL-2
Gardnersville Transformer #1 - 22kV Side
Gardnersville Transformer #2 - 22kV Side
Gardnesville - Redlight
Gardnesville - Johnsonville
Gardnesville - Stockton Creek
Gardnesville - Industrial Park
Kru Town Stockton Creek 66kV TL-1
Kru Town Bushrod 66kV TL-1
Kru Town Bushrod 66kV TL-2
Kru Town Capitol 66kV TL-1
Kru Town Capitol 66kV TL-2
Kru Town Transformer #1 - 22kV Side
Kru Town Transformer #2 - 22kV Side
Kru Town - Water & City
Kru Town - Mamba Point
Kru Town - USA
Kru Town - Vai Town
Paynesville Mt. Coffee 66kV TL-1
Paynesville Mt. Coffee 66kV TL-2
Paynesville Gardnersville 66kV TL-1
Paynesville Gardnersville 66kV TL-2
Payesville Kakata 66kV TL-1
Payesville Kakata 66kV TL-2
Paynesville Transformer #1 - 22kV Side
Paynesville Transformer #2 - 22kV Side
Paynesville - Redlight
Paynesville - Congo Town
Paynesville - Duport Road
Paynesville - Gate 15
Stockton Creek Bushrod 66kV TL-1
Stockton Creek Bushrod 66kV TL-2
Stockton Creek Gardnersville 66kV TL-1
Stockton Creek Gardnersville 66kV TL-2
Stockton Creek Capitol 66kV TL-1
Stockton Creek Capitol 66kV TL-2
Stockton Creek Kru Town 66kV TL-1
Stockton Creek Kru Town 66kV TL-2
Stockton Creek Transformer #2 - 22kV Side
Stockton Creek Transformer #1 - 22kV Side
Stockton - UCI Express
Stockton Creek - LPRC
Stockton Creek - New Georgia
Stockton Creek - CEMENCO
Stockton Creek - SETHI Express
Virginia Bushrod 66kV TL-1
Virginia Kle 66kV TL-1
Virginia Transformer #1 - 22kV Side
Virginia - Hotel Africa
Virginia - St. Paul Bridge
Virginia - Po. River
Kakata Paynesville 66kV TL-1
Kakata Transformer #1 - 33kV Side
Kakata Weala
Kakata Gate 15
Kle Virginia 66kV TL-1
Kle Transformer #1 - 33kV Side
Kle - Madina
Kle - Tubmanburg
Kle - Po. River
Capitol Stocton Creek 66kV TL-1
Capitol Stocton Creek 66kV TL-2
Capitol Congo Town 66kV TL-1
Capitol Congo Town 66kV TL-2
Capitol Transformer #1 - 22kV Side
Capitol Transformer #2 - 22kV Side
Capitol - Orange Express
Capitol - Congo Town
Capitol - Hill
Capitol - Kru Town
Congo Town Paynesville 66kV TL-1
Congo Town Paynesville 66kV TL-2
Congo Town Capitol 66kV TL-1
Congo Town Capitol 66kV TL-2
Congo Town Transformer #1 - 22kV Side
Congo Town Transformer #2 - 22kV Side
Congo Town - Ministerial Complex
Congo Town - Back Road
Congo Town - JFK
Congo Town - Matadi
Congo Town - Lone Star Express
Schieffelin Paynesville 66kV TL-1
Schieffelin Paynesville 66kV TL-2
Schieffelin RIA 66kV TL-1
Schieffelin RIA 66kV TL-2
Schieffelin Transformer #1 - 22kV Side
Schieffelin Transformer #2 - 22kV Side
Schieffelin - Seminary
Schieffelin - VOA
Schieffelin - Marshall
RIA Schieffelin 66kV TL-1
RIA Schieffelin 66kV TL-2
RIA Transformer #1 - 33kV Side
RIA Transformer #2 - 33kV Side
RIA - Express
RIA - St. John River
RIA - Charlesville
RIA - Unification City
Location
*
Outage Type
*
Please Select
Automated Forced Outage
Manual Forced Outage
Scheduled Outage
Start Date and Time
*
-
Month
-
Day
Year
2 digit month, 2 digit day, 4 digit year
Date
Hour Minutes
AM
PM
AM/PM Option
Standard Cause Identification
*
Please Select
Isolator Alignment
Interruption_by_Operation_and_or_Maintenance
To Retrieve Faulty Tx
Interruptions_caused_by_non_network_elements
Interruptions_due_to_transport_accidents
Material_or_Equipment_Failures
Vegetation Carry Out
To Restore Constant Tripping on Feeder
Interruptions_due_to_damages_in_other_public_services
To Reposition Broken H-Frame Pole
Interruptions_due_to_Generation_Failure
Interruption due to over current
interruption due to earth fault
interruption due to under frequency
interruption due to under voltage
Due to fire outbreak
To reclose close cutoff
Interruption due to over current & earth fault
Interruption due to over current & earth fault
Repairing of cut-jumper
To close Drop-OFF fuse manually
Tripped (O/C & E/F)
Changing of damaged arrester
Changing of damaged arrester
Closing Cut-Out mannually
Erection of MV pole
Erection of LV pole
Low_or_Indequate_Supply
Repairing of MV line, Cut jumper
Repairing of LV line, Cut jumper
To Tie in Jumper (Medium Voltage Line)
Tranformer 22/66 kv tripped
Tranformer 33/66 kv tripped
Tripped From CLSG Breaker
Tripped ( E/F)
Tripped (O/C)
To replace Cutoff Switch
To replace Breaker
Repairing Cutoff Switch
To tie in Tranformer 22/33 kv
To Close G. Switch (Medium Voltage Line)
To Open G. Switch (Medium Voltage Line)
To Reclose Cutoff Switch
To Open Cutoff Switch
22/33kv Line Diversion
To Couple 22/33kv Line
To Open Jumper (Medium Voltage Line)
To De-Couple 22/33kv Line
To Instilled Tx (Medium Voltage Line)
Strining 22/33kv Line
Cable Tremination ( 22/33kv Line)
To Close 22/33kv Line Extension (Medium Voltage Line)
To close Drop-OFF fuse manually
To Instilled G. Switch (Medium Voltage Line)
To Tie in 22/33kv Line Extension (Medium Voltage Line)
Arcing on 22/33 kv Tranformer
Safety Purpose
To Instilled Under Grand Cable
Erection of MV pole (Outage Request )
To Open 22/33kv Line Extension (Medium Voltage Line)
To Repairing Under Grand Cable
To Remove Pole (Medium Voltage Line)
To Replace damage Pole (Medium Voltage Line)
Due to fire outbreak on the Medium Voltage Line
To Lift aup Jumper (Medium Voltage Line)
To Change Cut Out Switch (Medium Voltage Line)
To Tie in Jumper (Medium Voltage Line)
Closing Cut-Out mannually
Arcing on 22/33 kv Line or Pannel
Arcing on 66 kv Line or Bus
Tripped From Mt. Coffee Plant
Cut-Out Adjustment
Tripped From Mt. coffee Hydro Power Plamt
To Repairing G. Switch (Medium Voltage Line)
Tripped From 22kv Tx (Medium Voltage Line)
To Close 22/33kv Line Extension (Medium Voltage Line)
To Put the 22/33kv Line on Full (Medium Voltage Line)
To remove 22kv/33kv Tx (Low Voltage/Medium Voltage Line)
To put the 22kv/33kv feeder on part (Medium Voltage Line)
To put the 22kv/33kv feeder on full (Medium Voltage Line)
To replacement of TX 22/33kv (Medium Voltage Line)
Trepped on TX 22/33kv (Medium Voltage Line)
SCADA Component installation
Substation Maintenance
Operation Safe Grid
Smart Meter Installation @Tx Substation
End Date and Time
*
-
Month
-
Day
Year
2 digit month, 2 digit day, 4 digit year
Date
Hour Minutes
AM
PM
AM/PM Option
Comment
*
Submit